UK Project 2023 : Liquid Biomethane Liquefaction – 2,100 Tons per Year

 

Plant Capacity: 2,100 Tons per Year

Feedstock: Cow manure + Food waste

 

Completed services:

 

Process design and engineering of the biogas pretreatment system, including:

  • Biogas Drying System

  • Heating system

  • Activated carbon filters for H₂S and VOCs elimination

  • LNG Filling station

 

Fabrication and Manufacturing Management

  • Biogas Dryer

  • Activated Carbon Filters

  • Compression Skid Operating at 1 Barg

  • Cooling System

  • LNG Filling Station

 

Control and Automation

  • Integrated PLC and SCADA system for full automation and monitoring of the solution

 

Systems Installed and Commissioned:

  • Pretreatment System

  • Biogas Upgrading Interconnection

  • CO₂ Polisher Interconnection

  • Biomethane Liquefier Interconnection

  • LNG Filling Station

 

MALYSIA Project 2025: Compressed Biomethane – 2,000 Tons per Year

 

Plant Capacity: 2,000 Tons per Year

Feedstock: Waste from Palm Oil Production

 

Completed services:

 

Process design and engineering of the biogas pretreatment system, including:

  • Biogas Drying System

  • Heating system

  • Activated carbon filters for H₂S elimination

 

Fabrication and Manufacturing Management

  • Biogas Dryer

  • Activated Carbon Filters

  • Compression Skid Operating at 1 Barg

  • Cooling System

 

 